sean
michael
mcalister



a diary of work from my daily work at grimshaw architects





Showing posts with label reference. Show all posts
Showing posts with label reference. Show all posts

apotheosis of king james

nazca airport iii

nazca airport

The Nazca Lines

The final highlight of our tour of Peru took place during our 2-night stay at Ica where we were given the opportunity to take a flight over the mysterious Nazca Lines. These are located on a desert plateau called the Pampa which stretches from Ica in the north down to the town of Nazca, about 80 miles to the southeast.The lines can be divided into three distinct types: the biomorphs, the geometric shapes and the straight lines. The biomorphs are the drawings of birds, fish, animals and insects and have been shown to be the oldest of the lines and are probably the most famous. There are around 50 of them which makes them the least common type. They come in various sizes from just 25m all the way up to 275m. One characteristic that they have in common is that they have each been drawn using a single, uninterrupted line which never crosses itself. This seems quite deliberate and has led to theories that the lines were used as ceremonial walkways.This desert plateau has been called “the greatest scratch pad on earth” because it is littered with a staggering collection of geoglyphs - huge lines, shapes and drawings that were scratched onto the desert surface around two thousand years ago by the ancient Nazcans. There are wide ranging estimates as to exactly how old the lines are but they all agree that they were created over a long period of time - at least 500 years.
These biomorphs, however, are dwarfed by the sheer number and phenomenal size of the geometric shapes and the straight lines. There are around 300 geometric shapes and around 800 straight lines on the Pampa. The geometric shapes include enormous triangles, rectangles and trapeziums that are hundreds of metres wide and thousands of metres long and these huge shapes often cross or interconnect with each other for complex but so far unfathomable reasons. The straight lines are quite narrow but they are usually many miles long and perfectly straight with the longest being about 9 miles (15km).

object impact

photo of chaos

aerial photograph of site's current[ish] condition [ as of 09..2010 ]

entire baggage system from siemens baggage consultants

ccc scope of services

SCOPE OF SERVICES – DRAFT 14.06.10
Cross Campus Connectivity Baggage Basements and Tunnels to T2A

The Cross Campus Connectivity (CCC) study will investigate the constructability implications and options of the proposed Baggage Tunnels and Basements which are required to connect T2A to the wider Heathrow Campus (T1, T3, T4 and T5). The T1 baggage systems will remain operational until the T2A baggage systems are commissioned and fully functional.

During the briefing meeting held on the 12th May 2010 with Edgar Vila Pouca additional scope of works were identified as described below.

The study will use Siemens MP6 Baggage options as baseline this information will be required prior to commencement of the works in AutoCAD format.
The findings of the study will be compiled into a report and identify any further study requirements. This document will be issued in PDF format, printed colour copies of the report has been excluded from the fee detailed below.
It should be noted that the proposed new baggage systems design may need to be adjusted to facilitate construction of the basements and tunnel connections, this scope works is excluded from this study.
This scope of services makes limited provision for Technical Leadership and Stakeholder Engagement, including attending 2 workshops
Costing advice is excluded from this scope and will be provided by BAA and EC Harris
Study to consider the following scope of works:
  1. Cross Campus Connectivity (CCC) Baggage Basement Systems feasibility study
  2. Baggage system integration within T2A Phase2 basement; test the volume requirements for the baggage system
  3. Terminal 1 Stage 1 cut line Validation: Test the extent of the Northern Boundary of the Baggage Basement to T2A
  4. T2A Phase3 safeguarding; test Cross Campus Connectivity Baggage Basements in relation to the construction of T2A Phase 3 or T2A Pier to serve the northern stands
  5. VPM connection to TTS station box interface study; consider alternative basement levels for the base of the TTS station box 12 and 18
  6. Fire Fighting Access and Evacuation Strategy for T2A Phase 2 basements
Study to include the following basement areas:
  1. o T2A Phase2 basement
  2. o T2A Phase2 TTS station box and associated tunnels
  3. o T2A Phase2 Early Bag Store and associated tunnels
  4. o T4 Interface baggage basement and associated tunnel
  5. o EIB basement chamber and associated tunnel
  6. o DCV deceleration zone basement
  7. o Baggage interface basement
  1. Smoke Extract Strategy for T2A Phase 2 basements
  2. Technical Leadership and Stakeholder Engagement

SCOPE OF SERVICES – DRAFT 14.06.10

Cross Campus Connectivity Baggage Basements and Tunnels to T2A

CONSULTANT TEAM STRUCTURE

  • Construction logistics and programming (Balfour Beatty)
  • Buildability advice (Balfour Beatty)
  • Architecture (Grimshaw)
  • Phasing Diagrams (time slices) (Balfour Beatty / Grimshaw)
  • Structure integration (Mott MacDonald Structures)
  • Services integration (WSP)
  • Evacuation Strategy (Exova)
  • Rail Engineering (Mott MacDonald Rail)

CLIENT TEAM INPUT

  • Roads / Access – Airfield Operations (BAA)
  • Pavements and Infrastructure Team (BAA)
  • Services and Infrastructure Team (BAA)
  • TTS Operating Group (BAA)
  • Fire (BAA)
  • Baggage Consultant (Siemens)
  • EDF

GRIMSHAW SCOPE OF SERVICES


1. Cross Campus Connectivity (CCC) Baggage Basement Systems feasibility study

Grimshaw to:
• Assess the feasibility of the proposed CCC basements and produce architectural layouts (plans and sections)
Input information required:
  1. o Baggage advice and layouts (Siemens)
  2. o Planning layouts for T2A (BAA / Foster and Partners)
  3. o General Arrangement drawings for T2A Phase1 (BAA / HETCo)
  4. o Structure and services drawings for T2A Phase1 (BAA / HETCo)
  5. o T1 Plans with proposed demolition cut lines (BAA / Grimshaw)
  6. o T1 Existing drawings including Basements (BAA / Grimshaw)
  7. o EIB basement detailed architecture, structure and services drawings (BAA)
  8. o Existing baggage tunnels basements setting out drawings (BAA)
  9. o Construction Logistics and Programming (Balfour Beatty)
  10. o Buildability and Phasing advice (Balfour Beatty)
  11. o Structural advice on setting out new basement adjacent T1 (Mott MacDonald Structures)
  12. o Structural advice in relation to proposed new basement construction (Mott MacDonald Structures)
  13. o Specialist advice on the sensitivity of the baggage systems required to assist structural design (BAA)

SCOPE OF SERVICES – DRAFT 14.06.10

Cross Campus Connectivity Baggage Basements and Tunnels to T2A

  1. o Services advice in relation to proposed new basement services requirements (WSP)
  2. o Fire Strategy advice in relation to proposed new basement evacuation strategy (Exovia)

• Assist in the production of Phasing diagrams for works (time slices)
Input information required:
  1. o Airfield road access advice to understand road phasing for baggage transfer from T4 to T1 (BAA)
  2. o Construction Logistics and Programming (Balfour Beatty)
  3. o Buildability and Phasing advice (Balfour Beatty)
• Compile Report illustrating the findings of the study
Input information required:
  1. o Architectural Plans and sections and assumptions
  2. o Balfour Beatty advice and production of programme
  3. o Balfour Beatty advice and production of buildability and logistics strategy
  4. o Phasing Diagrams
  5. o Siemens baggage findings and assumptions
  6. o Structural findings and assumptions
  7. o Services findings and assumptions
  8. o Fire Strategy findings and assumptions
  9. o Airfield road access findings and assumptions
2. Baggage system integration within T2A Phase2 basement; test the volume requirements for the baggage system
Grimshaw to:
• Assess the volumetric requirements for the proposed baggage basement systems against the existing T2A Phase2 drawings conclusions drawn will inform size / depth allocation for the basement construction
Input information required:
  1. o Baggage advice and layouts (Siemens)
  2. o Planning layouts for T2A (BAA / Foster and Partners)
  3. o General Arrangement drawings for T2A Phase1 (BAA / HETCo)
  4. o Structure and services drawings for T2A Phase1 (BAA / HETCo)
  5. o Construction Logistics and Programming (Balfour Beatty)
  6. o Buildability and Phasing advice (Balfour Beatty)
  7. o Structural advice in relation to proposed new basement construction (Mott MacDonald Structures)
  8. o Services advice in relation to proposed new basement services requirements (WSP)
  9. o Fire Strategy advice in relation to proposed new basement evacuation strategy (Exovia)
3. Terminal 1 Stage 1 cut line Validation: Test the extent of the Northern Boundary of the Baggage Basement to T2A
Grimshaw to:

SCOPE OF SERVICES – DRAFT 14.06.10

Cross Campus Connectivity Baggage Basements and Tunnels to T2A

Assess the proposed Terminal 1 Stage 1 cut line and the northern boundary of the T2A Baggage Basement, conclusions drawn will inform size / depth allocation for the basement construction

Input information required:
  1. o Baggage advice and layouts (Siemens)
  2. o Planning layouts for T2A (BAA / Foster and Partners)
  3. o General Arrangement drawings for T2A Phase1 (BAA / HETCo)
  4. o Structure and services drawings for T2A Phase1 (BAA / HETCo)
  5. o T1 Plans with proposed demolition cut lines (BAA / Grimshaw)
  6. o T1 Existing drawings including Basements (BAA / Grimshaw)
  7. o Construction Logistics and Programming (Balfour Beatty)
  8. o Buildability and Phasing advice (Balfour Beatty)
  9. o Structural advice on setting out new basement adjacent T1 (Mott MacDonald Structures)
  10. o Structural advice in relation to proposed new basement construction (Mott MacDonald Structures)
  11. o Specialist advice on the sensitivity of the baggage systems required to assist structural design (BAA)
  12. o Services advice in relation to proposed new basement services requirements (WSP)
  13. o Fire Strategy advice in relation to proposed new basement evacuation strategy (Exovia)
4. T2A Phase3 safeguarding; test Cross Campus Connectivity Baggage Basements in relation to the construction of T2A Phase 3 or T2A Pier to serve the northern stands
Grimshaw to:
• Assess the implications of the possible T2A Phase3 building constraints over the proposed CCC baggage basements
Input information required:
  1. o BAA briefing relative to future options Phase 3
  2. o Baggage advice and layouts (Siemens)
  3. o Construction Logistics and Programming (Balfour Beatty)
  4. o Buildability and Phasing advice (Balfour Beatty)
  5. o Structural advice on setting out new basement adjacent T1 (Mott MacDonald Structures)
  6. o Structural advice in relation to proposed new basement construction (Mott MacDonald Structures)
  7. o Specialist advice on the sensitivity of the baggage systems required to assist structural design (BAA)
  8. o Services advice in relation to proposed new basement services requirements (WSP)
  9. o Fire Strategy advice in relation to proposed new basement evacuation strategy (Exovia)
• Assess the implications of the possible T2A Pier to serve the northern stands building constraints over the proposed CCC baggage basements

SCOPE OF SERVICES – DRAFT 14.06.10

Cross Campus Connectivity Baggage Basements and Tunnels to T2A

Input information required:

  1. o BAA briefing relative to future options possible T2A Pier to serve the northern stands
  2. o Baggage advice and layouts (Siemens)
  3. o Construction Logistics and Programming (Balfour Beatty)
  4. o Buildability and Phasing advice (Balfour Beatty)
  5. o Structural advice on setting out new basement adjacent T1 (Mott MacDonald Structures)
  6. o Structural advice in relation to proposed new basement construction (Mott MacDonald Structures)
  7. o Specialist advice on the sensitivity of the baggage systems required to assist structural design (BAA)
  8. o Services advice in relation to proposed new basement services requirements (WSP)
  9. o Fire Strategy advice in relation to proposed new basement evacuation strategy (Exovia)
5. VPM connection to TTS station box interface study; consider alternative basement levels for the base of the TTS station box 12 and 18
Grimshaw to:
• Assess alternative options in relation to the passenger connectivity between the VPM basement and the TTS station box
Input information required:
  1. o General Arrangement drawings for the VPM buildine (BAA / HETCo)
  2. o BAA Passenger movement advice (BAA)
  3. o Structural advice in relation to proposed connections (Mott MacDonald Structures)
  4. o Services advice Services advice in relation to proposed connections (WSP)
  5. o Fire Strategy advice in relation to proposed connections (Exovia)
  6. o TTS engineering advice (BAA)
6. Fire Fighting Access and Evacuation Strategy for T2A basements
Grimshaw to:
    • Assist Exova in developing a preliminary fire fighting and evacuations strategy for the T2A Phase2 basements to include the following building areas:
      1. o T2A Phase2 basement
      2. o T2A Phase2 TTS station box and associated tunnels
      3. o T2A Phase2 Early Bag Store and associated tunnels
      4. o T4 Interface baggage basement and associated tunnel
      5. o EIB basement chamber and associated tunnel
      6. o DCV deceleration zone basement
      7. o Baggage interface basement
  • To provide diagrammatic plans to illustrate the above strategy
Input information required:

SCOPE OF SERVICES – DRAFT 14.06.10

Cross Campus Connectivity Baggage Basements and Tunnels to T2A

  1. o Fire Strategy advice in relation to proposed new basement evacuation strategy
  2. o Services advise

7. Smoke Extract Strategy for T2A Phase 2 basements
Grimshaw to:
• Assist Exova and WSP to develop preliminary smoke extract strategy for the T2A Phase2 basements to include the following building areas:
  1. o T2A Phase2 basement
  2. o T2A Phase2 TTS station box and associated tunnels
  3. o T2A Phase2 Early Bag Store and associated tunnels
  4. o T4 Interface baggage basement and associated tunnel
  5. o EIB basement chamber and associated tunnel
  6. o DCV deceleration zone basement
  7. o Baggage interface basement
8. Technical Leadership and Stakeholder Engagement
Grimshaw to:
• Assist Balfour Beatty the process of Technical Leadership and Stakeholder Engagement this will be limited to attending 2 number workshops
Input information required:
  1. o Balfour Beatty and BAA to determine extent of Technical Leadership engagement
  2. o Balfour Beatty and BAA to determine extent of Engagement

ASSUMPTIONS


  • All basements will be constructed as part of Phase 2 where construction will commence early 2015
  • Assume T1 demolition cuts lines as detailed in the T2A Phase2 constructability study (December 2009) Assume T1 Pier 3 aircraft stands can be decommissioned early 2015
  • Assume T1 – T4 baggage tunnel will be switched off for a period of time in order to make new connection to the T4 baggage interface basement, transfer bags will be moved by vehicle above ground, Airside road access will be required to serve T1 baggage facility
  • T3 / T5 – T1 baggage tunnel and basement chamber of the Eastern Interface Building (EIB) are existing (baggage system will be installed during phase2 works)

SCOPE OF SERVICES – DRAFT 14.06.10

Cross Campus Connectivity Baggage Basements and Tunnels to T2A

  • It is assumed that the T1 baggage systems will remain operational until the T2A baggage systems are commissioned and fully functional. Specialist advice on the sensitivity of the baggage systems will be required to assist in resolving a structural solution for the constructability and phasing to this area.
  • It is assumed that a space factor will be added to the current baggage volumes for fire escapes, smoke extracts, safety zoning and sprinkler zone. There is a degree of risk in this assumption which will need to be addressed at a later phase of the design.

EXTENT OF DELIVERABLES


  • Attend weekly workshop meetings
  • Produce Plans and sections (issued in PDF format)
  • Produce 3d sketchup model to assist explanation of scheme (issued in PDF format)
  • Collate Report of study findings (issued in CD format)
  • Attend 2 number Technical Leadership and Stakeholder Engagement workshops

PROGRAMME

Commence 28th June 2010 (18 week Programme)

Complete 29th October 2010

GRIMSHAW FEE PROPOSAL